A sponsor decides that the business environment is unfavorable for continuation of a program.
The sponsor asks that the program be closed.
What items should be completed as part of the program's final report?
The sponsor asks that the program be closed.
What items should be completed as part of the program's final report?
정답: D
To increase its presence and promote its products and services in new markets, a company begins to implement its new business strategy. The company's CEO endorses a new program to promote and support this strategy However before the program is formally initialed, this strategy must be aligned with the organization's strategic goals and objectives.
What should the program manager develop first?
What should the program manager develop first?
정답: B
A project is assigned to a qualified project manager by the program manager I he client rejects the project manager due to a lack of proper qualifications to manage such a project What should the program manager do next?
정답: A
Which of the following is a method that an ICT distribution designer would use for clash detection with other disciplines?
정답: B
The program director of a four-year program, estimated to require 600.000 person-days effort, notices that team morale has decreased over the last three months. The program is at a critical stage with 70% completion through the last phase. A number of defects are found that result in teams working additional hours. The program director requests that the program management office (PMO) gather metrics to monitor the situation Which of the following metrics should the PMO capture on a monthly basis?
정답: A
A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet What activity should the program manager perform next?
정답: D
In which phase of the protect design would an ICT distribution designer be expected to prepare preliminary cost estimates?
정답: B
Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.
What should be done with the identified potential risk?
What should be done with the identified potential risk?
정답: B
The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?
In this situation, what should the program manager change about the risk management plan?
정답: D