최신 PSP 무료덤프 - ASIS Physical Security Professional

Determine the correct formula and date for the late finish for Activity 6002.

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
How could the structural steel drawing delay have been prevented?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Which of the following is NOT true?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

정답: D
Which of the following statements is true?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which of the following is NOT required when performing weekly or monthly schedule updates?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Using the normal schedule and excluding general conditions, which activities are NOT on the critical path?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
What is the cycle time?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)

우리와 연락하기

문의할 점이 있으시면 메일을 보내오세요. 12시간이내에 답장드리도록 하고 있습니다.

근무시간: ( UTC+9 ) 9:00-24:00
월요일~토요일

서포트: 바로 연락하기