최신 PMI-ACP 무료덤프 - PMI Agile Certified Practitioner
While planning, what prioritization factors need to be considered for a minimally marketable feature (MMF)?
정답: A
Midway through an iteration an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?
정답: B
A scrum team has eight developers, but only two are database engineers. During the last few retrospectives, the team identified that most sprint stories are dependent upon database engineers. This has created a bottleneck in completing stories.
What should be proposed to the team?
What should be proposed to the team?
정답: D
A key stakeholder cannot attend the project vision statement development workshop. The stakeholder has emailed their requirements to the agile team lead, and believes that the vision statement is not critical.
How should the agile team lead respond?
How should the agile team lead respond?
정답: B
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?
What should the agile practitioner do?
정답: D
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company's steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
What is the estimated project conclusion?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which agile practice would most significantly increase a team's velocity?
정답: B
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?
정답: D
During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact.
The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.
What should the scrum master do now?
The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.
What should the scrum master do now?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.
What agile practice can help the team to alleviate this?
What agile practice can help the team to alleviate this?
정답: C
An agile learn has only one database administrator with the necessary knowledge of database-related tasks.
The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
정답: A
A new team member asks what changes could accelerate a change to the project plan What should be the proper response?
정답: B
A new product owner needs to manage the backlog of a high-visibility fast-moving project that is consuming a considerable amount of time What should the product owner do?
정답: A
The agile team disagrees with the business stakeholders on completing some epics What could help eliminate misunderstandings?
정답: A
A team member has asked a question about the responsibilities of the product manager, QA, and the team regarding quality. What should the agile project manager advise?
정답: A
What should a learn consider when calculating the effort needed to complete a product backlog?
정답: B
A new agile team is forming to address a high-priority project. Team members are dispersed over a wide geographic area. The scrum master and the team are currently defining their working agreement.
What should be part of the working agreement for a dispersed team?
What should be part of the working agreement for a dispersed team?
정답: C