최신 PK0-004 무료덤프 - CompTIA Project+ Certification

A project is moving into the next phase, and those involved with planning will not actually perform the work.
After the project team members have been identified and assigned to do the work, which of the following has changed?

정답: D
Everyone on the team agrees with a change request, and the team proceeds with the implementation. Which of the following steps is missing from the identified process?

정답: D
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?

정답: D
Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

정답: A
During an ad-hoc meeting, the OM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?

정답: C
An individual is responsible for the training and education for a new product in a strong matrix organization. Which of the following roles does this describe?

정답: D
A company wants to remodel two areas in a building it is leasing. The company will utilize its own contractors to remodel the areas. The building owners agree to the remodel. Which of the following documents would the owners MOST likely utilize with the business?

정답: C
A program manager informs a project manager that a new, high-priority project has been approved and will need the current project's resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)

정답: A,E
A project manager is sending regular status reports; however, many team members seem to be unaware of the overall project status. Which of the following should the project manager do NEXT?

정답: C
Project cost control deals with:

정답: C
Before a team can start on a sprint, they will need to:

정답: D
Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned.
Which of the following risk strategies was used?

정답: C
At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified.
Which of the following risk activities is MOST likely missing since the identification?

정답: B
Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.)

정답: D,E
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

Which of the following is the NEXT appropriate step for the project manager to take?

정답: C
A new project has just commenced. Project team members are constantly disagreeing on how tasks should be handled and are not getting along well. Which of the following stages BEST explains this situation?

정답: D
A functional manager within a project is requesting to edit the display features of an application that is being developed.
Which of the following has the authority to approve the edit?

정답: B
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?

정답: A
An influential stakeholder has left the organization. Which of the following documents MOST likely needs to be updated?

정답: C
Which of the following should receive regular communication during the planning phase of a project? (Choose two.)

정답: C,E

우리와 연락하기

문의할 점이 있으시면 메일을 보내오세요. 12시간이내에 답장드리도록 하고 있습니다.

근무시간: ( UTC+9 ) 9:00-24:00
월요일~토요일

서포트: 바로 연락하기