You are preparing for a standard SAP S/4HANA conversion from SAP ECC on Windows with SAP MaxDB to SAP S/4HAN. You are performing the corresponding maintenance transaction with the Maintenance Planner. Which kernels do you need to select for the SAP S/4HANA conversion?
There are 2 correct answers to this question.

정답: B,C
Which preparational steps must be performed for an SAP S/4HANA conversion?
There are 2 correct answers to this question.
Response:

정답: B,D
You are performing an upgrade with SUM. You are in the BIND_PATCH phase of the roadmap step "Configuration". For some software components you find entries in the "Calculated level" column.
What does the "Calculated level" indicate for those software components?
Please choose the correct answer.
Response:

정답: C
You performed a custom code check for an SAP S/4HANA conversion. In which transactions can you review the results?
There are 2 correct answers to this question.
Response:

정답: B,C
Which steps should be performed during the adjustment of dictionary objects (SPDD) in the development system, before SUM continues?
There are 2 correct answers to this question.
Response:

정답: B,C
You are performing an SAP S/4HANA conversion with DMO. You are using the downtime-optimized data conversion (DoC). Which steps can partially be moved to uptime processing? Note: There are 2 correct answers to this question.

정답: B,C
In ICNV. How database operations synchronized between the source and the target table?

정답: B
You want to use the downtime-optimized data conversion for your SAP S/4HANA conversion. What is the main difference from a standard SAP S/4HANA conversion?
Please choose the correct answer.
Response:

정답: A