최신 CCP 무료덤프 - AACE International Certified Cost Professional (CCP)
AACE International defines_____________as the primary activity that separates Value Methodology (VM) from other "improvement" practices and has the objective to develop the most beneficial areas for continuing study.
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the relative frequency of unit costs amounting to $55.00/unit?
What is the relative frequency of unit costs amounting to $55.00/unit?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
You are reporting the following Earned Value Analysis information for the project:
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
EV= $1,500,000
AC=$1.000,000
PV= $2,000,000
What is the status of the project?
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Money is value Having money when you need it is very important Money can also be valuable when used wisely by knowing when to spend and when to conserve. Also. planning now for future expenses can be a plus to the company rather than a debit. There are several ways to capitalize money and spending. Basically, there is the single payment mothed that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capita1 recovery factor and also the compound amount factor and present worth factor. At this point, we can assume money is worth 10%.
Which of the following is not one of the requirements to form a contract?
Which of the following is not one of the requirements to form a contract?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.
Cost engineers who feel completely satisfied and fulfilled by their work as part of a project team are said to have reached the ______________ stage of Maslow's hierarchy of needs.
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.
What is the range of unit costs?
What is the range of unit costs?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A work breakdown structure (WBS) is developed because:
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.
The following revenue and expense relationships are predicted:

If the fixed rent remains unchanged, and XYZ pays S0.01 per unit as additional rent, the monthly breakeven point in numbers of units becomes:
The following revenue and expense relationships are predicted:

If the fixed rent remains unchanged, and XYZ pays S0.01 per unit as additional rent, the monthly breakeven point in numbers of units becomes:
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
The measure of number of units completed divided by work-hours consumed is referred to as:
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
If a project is said to be on a "fast track program/' the fast track method is:
정답: D
설명: (DumpTOP 회원만 볼 수 있음)