You select the master data for production orders via production versions.
Which information is contained in a production version?
Which information is contained in a production version?
정답: C
A user you advise wishes to transfer variable process instructions for automated processing directly to certain work centers and machines in the production department (for example, feed speed, pressing pressure, dry temperature). The user also wishes to receive variable as-is messages (such as actual quantities, actual times) from these work centers and machines and to process these messages for feedback concerning production orders. Which of the following options would you recommend to implement these requirements?
정답: B
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
정답: A,D,E
When maintaining a work center, formulas can be assigned in the scheduling view. Formulas use formula parameters for calculation.
What can be the origin of the formula parameters used for scheduling? (Choose three)
What can be the origin of the formula parameters used for scheduling? (Choose three)
정답: A,C,E
An enterprise wants to use SAP ECC requirements planning together with the NETPL procedure (net change planning in the planning horizon). The planning horizon is to be set equally for all materials by default.
However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the system side?
However, some materials are to be given a different planning horizon.
What procedure would you recommend to the project team for setting the planning horizon on the system side?
정답: A
Which of the following properties applies to multi-site planning in SAP ECC?
정답: A
Which of the following statements about the planning functions available in SAP ECC is correct?
정답: A
You want to use the different options for planning in SAP ECC.
What is the correct sequence of the planning procedures?
What is the correct sequence of the planning procedures?
정답: D