Which of the following objects can you release so that the business transactions for process order execution and process management can be executed?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
정답: B,C
Which data object can be updated with the scheduling results of a routing?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
정답: C
What is the first step in the MRP run?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
정답: C
What are pillars of SAP Activate?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
정답: B,D
Which of the following functions can be performed when the production order has the status "Created" (CRTD)?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
정답: A
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
정답: B
What must be used in the system to plan the requirements for different subcontractors separately?
Response:
Response:
정답: D
What are drawbacks of the separation of OLTP and OLAP?
There are 4 correct answers to this question.
Response:
There are 4 correct answers to this question.
Response:
정답: A,B,C,E
You produce your material based on a forecast derived from historical sales and expect it to be in inventory when your customer orders. If customers order more that the forecasted quantity, you want to increase production to try to meet the extra demand.
Which is the appropriate planning strategy to use?
Response:
Which is the appropriate planning strategy to use?
Response:
정답: A