In SAP documentation for MRP in Advanced Planning, you read that the MRP creates new planned orders through infinite scheduling. What does this mean for the capacity requirements of the new planned order?

정답: B
Your production planners are supposed to execute planning only for specific resources. What do you use to achieve this in Advanced Planning (PP/DS)?

정답: D
What are the selection criteria of a bill of material (BOM) alternative?
Note: There are 2 correct answers to this question.

정답: B,C
What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.

정답: A,C
You are trying to create a production order and no valid production version can be selected. What could be the reasons?
Note: There are 2 correct answers to this question.

정답: A,D
What is a prerequisite for the consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?

정답: A
How would you define a pegging structure for an order in the context of Advanced Planning?

정답: A
Which of the following are scheduling time elements for a production order?
Note: There are 3 correct answers to this question.

정답: A,D,E
What will happen in the MRP run if you have created a new MRP-relevant material that supports both in-house production and external procurement?

정답: A