최신 AACE-PSP 무료덤프 - AACE International Planning & Scheduling Professional (PSP)

Which of the following is NOT required when initially planning a project?

정답: B
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

정답: D
Assumptions made during the planning stage should be_____________.

정답: A
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

정답: C
Determine the correct formula and date for the late finish for Activity 6002.

정답: B
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?

정답: B
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

정답: D
Which of the following phases does NOT describe the commonly accepted construction life cycle?

정답: A
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the "normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

정답: C
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?

정답: A