You are in the process of defining a Standard Operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Identify the setup that will fulfill this requirement.
Identify the setup that will fulfill this requirement.
정답: D
While creating an item in Product Information Management (PIM), the following two item templates are selected in sequence and applied.
1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.
1. Template: Finished Goods (WIP = No, Customer Ordered = Yes)
2. Template: Sub-assembly (WIP = Yes, Customer Ordered = No)
Identify the Item Attribute values in the application.
정답: B
The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.
Identify the correct sequence of steps to achieve this requirement.
정답: B
A Production operator in your company is required to report production activities, such as completing or scrapping production units, by referencing a work definition without creating work orders.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
정답: E
A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs.
Identify the two recommendations.
Identify the two recommendations.
정답: A,C
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.
정답: A,C
Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the Manufacturing Cloud?
정답: B,D
설명: (DumpTOP 회원만 볼 수 있음)