최신 074-344 무료덤프 - Microsoft Managing Programs and Projects with Project Server 2013
You are a project manager for an organization that uses Project Server 2013 with Project Professional 2013.
The stakeholders on your project want to easily view the issues related to tasks on your project schedule from within Project Center.
You need to allow the stakeholders to view the related issues.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
The stakeholders on your project want to easily view the issues related to tasks on your project schedule from within Project Center.
You need to allow the stakeholders to view the related issues.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
정답: C,D
설명: (DumpTOP 회원만 볼 수 있음)
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You review your organization's issue management process.
You need to implement a new issue management process that meets the following requirements:
--
All issues for future projects need to be associated with a source. Source values are either Internal or External.
What should you do?
You review your organization's issue management process.
You need to implement a new issue management process that meets the following requirements:
--
All issues for future projects need to be associated with a source. Source values are either Internal or External.
What should you do?
정답: D
You are a project manager for an organization that uses Project Server 2013.
You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules.
You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks.
What should you do?
You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules.
You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks.
What should you do?
정답: D
Your work in a multinational corporation which uses Project Server 2013 to plan and control projects in different business units. Each business unit has its own portfolio of projects but can participate in strategic projects. The Project Management Office (PMO) has configured
Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general information about the new product by efficiently collaborating with the local team.
What should you do?
Enterprise Project Types (EPTs) to create new products, launch marketing campaigns, and deploy new lines of business tools to comply with the governance processes.
One of your roles is to identify new products. A local team in Singapore produces an effective idea for a new product.
You need to create a business case for the next portfolio analysis. You need to gather general information about the new product by efficiently collaborating with the local team.
What should you do?
정답: B
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. The Project Site Provisioning Mode for your organization allows users to choose when to provision project sites.
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?
You use Project Web App (PWA) to create a new enterprise project named Sub1 that will be inserted as a subproject in your existing master project named Master.
You need to create a new project site for Sub1 as a subsite of the existing Master Project Site.
What should you do?
정답: C
You work for an organization that uses Project Server 2013. Single-entry mode is disabled.
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
During week one, a team member enters a total of 20 hours of actual work.
During week two, the team member modifies the total to 30 hours of actual work.
Following a save, the work value remains the same, and the remaining work value
decreases.
Additionally, the percent of work complete increases.
Which tracking method should you use?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
You are a project administrator and are implementing Project Server 2013 for a large organization.
You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure.
You need employ the correct functionality in order to configure Project Server 2013.
What should you do?
You are asked to ensure that resource assignments, work load, and completion of work can be reported and rolled up by organizational structure.
You need employ the correct functionality in order to configure Project Server 2013.
What should you do?
정답: D
You are a project manager who uses Project Server 2013.
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
You have an in-progress project. A resource who has reported actual work on the project is no longer available. You want to preserve their actual work.
You need to replace this resource with a newly-hired resource.
What should you do?
정답: A
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013.
You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
-- --
Review the project data after the project managers create the projects.
Send the projects back to the project managers if you find incorrect data so that
they can make the appropriate corrections.
Repeat the data verification process unless the data does not have any errors.
Publish a project only when all of its data is correctly completed.
What should you do?
You notice that some projects have been published with incorrect data. You and the project managers spend a lot of time correcting the data problems.
You need to implement a new project creation process which does not affect the projects that are already created and which allows you to perform the following actions:
-- --
Review the project data after the project managers create the projects.
Send the projects back to the project managers if you find incorrect data so that
they can make the appropriate corrections.
Repeat the data verification process unless the data does not have any errors.
Publish a project only when all of its data is correctly completed.
What should you do?
정답: B
You are a program manager in the Project Management Office (PMO) of an organization that uses Project Server 2013. Project Server Permission Mode is enabled.
You create a new project enterprise custom field and a Project Center view.
Project managers report that they cannot see the new view in the Views dropdown box in Project Center. However, they can see other views.
You need to enable the project managers to see the new view.
What should you do?
You create a new project enterprise custom field and a Project Center view.
Project managers report that they cannot see the new view in the Views dropdown box in Project Center. However, they can see other views.
You need to enable the project managers to see the new view.
What should you do?
정답: D