최신 070-348 무료덤프 - Microsoft Managing Projects and Portfolios with Microsoft PPM

HOTSPOT
You are a project manager and want to display key deliverables associated with your project. The tasks that produce the deliverables are already on the project schedule.
You need to ensure that the deliverables are visible on the project site.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.
정답:

Explanation:

References:
https://diegocampereira.com/2017/02/10/creating-deliverables-using-microsoft-project- professional-and-project-site/
Your organization is using Microsoft PPM to manage and track all projects.
The Project Management Office (PMO) needs to know which of the projects are aligned to the organization's strategic objectives.
You need to configure Microsoft PPM to use Portfolio Analysis.
Which two activities should you perform? Each correct answer presents part of the solution.

정답: B,D
설명: (DumpTOP 회원만 볼 수 있음)
An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis.
You need to ensure that resources can enter their time on tasks.
Which three actions should you take? Each correct answer presents part of the solution.

정답: A,B,D
HOTSPOT
You are the project manager for a real estate management company. You are using
Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
정답:
DRAG DROP
You are a program manager who is using Microsoft PPM and Microsoft Project to manage an e-commerce portal development program.
The program is separated into individual projects that represent each area of development, so that each group can manage its own tasks while still having progress visibility at the program level.
You need to be able to manage the overall program as well as its associated individual projects within Project Center. This includes the project sites associated with both the program and the individual projects. Each individual project site should be a subsite of the overall program project site.
You need to create the master program, the individual projects, and their associated project sites.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.
정답: