You are a test manager managing a test team and working at a government agency. The test team is responsible for performing the system test. Senior management has been provided with the following test objective for a new project:
"The system should be of high quality."
Using the SMART goal methodology, which of the following statements would be appropriate as a revision to the defined test objective by management?
"The system should be of high quality."
Using the SMART goal methodology, which of the following statements would be appropriate as a revision to the defined test objective by management?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Following up on the situation, the team lacks drive and is performing tasks too slowly. You have been asked to recruit an extra person into the team. Which of the following team roles would be most appropriate to enhance the team?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
Which of the following statements about test management activities for an iterative development model is false?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
A project has been running for a few months and the team does not seem to be making progress in their test approach. The team also lacks drive and enthusiasm and is sometimes seen to be performing their tasks too slowly. You have been asked to recruit an extra person into the team. In addition to introducing the new team member, you have decided to raise motivation.
Which of the actions listed below would most likely result in the opposite, a de-motivation of the team?
Which of the actions listed below would most likely result in the opposite, a de-motivation of the team?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Management is sceptical regarding the budget request (€25,000) for the next testing project. You are asked for a cost-benefit calculation. Based on historical data from several projects, you have come up with the following numbers:
Average prevention cost per defect: €200
Average cost of detection per defect: €400
Average cost of internal failure: €150
Average cost of external failure: €2,500
Expected number of defects to be found in this project during testing: 50 What is the result for the expected cost-benefit calculation for the upcoming project?
Average prevention cost per defect: €200
Average cost of detection per defect: €400
Average cost of internal failure: €150
Average cost of external failure: €2,500
Expected number of defects to be found in this project during testing: 50 What is the result for the expected cost-benefit calculation for the upcoming project?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which of the following is a generic good practice in adopting and rolling out of a new test tool?
정답: A
설명: (DumpTOP 회원만 볼 수 있음)