최신 PMI-SP 무료덤프 - PMI Scheduling Professional
You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit status reports every week, but now he wants you to submit the status reports every other week. What project management plan would you need to update to reflect this change from Thomas?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager of the NHQ project. This project deals with a new technology that your company has never used before. You have petitioned the management to hire a consultant to help you and the project team to create the WBS, the activity list, and complete the duration estimates. The management is concerned about the costs of the consultant, but agrees to your request because of the nature of this new work. The consultant can best be described as what type of resource for this project?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
What is the term assigned to graphic in the figure given below?


정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedule performance index?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.
Management needs a performance report regarding the NHQ project. What is the planned value for this project?
Management needs a performance report regarding the NHQ project. What is the planned value for this project?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below: What is the cost performance index (CPI) of the project at the current point of time?


정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager for your organization. You have worked with the project team to create the project scope statement. The key stakeholders have signed off on the project scope and they are eager for you and the project team to begin creating the deliverables identified within
the project scope. What process must you and the project team complete next in this scenario?
the project scope. What process must you and the project team complete next in this scenario?
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
If you are the project manager of the BNQ Project and you add "waiting time" between two activities, then what have you added in the project?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are up posed to be at your second milestone which accounts for half of the project completion. There have been some errors in the project which has caused you to spend $2,073,654. What is this project's schedule variance?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
John is a scheduler in ABC Company. He has to plan an activity for the schedule models. Which of the following activities will he use to make the schedule models? . Each correct answer represents a complete solution. Choose all that apply.
정답: A,C,D
설명: (DumpTOP 회원만 볼 수 있음)
Complete this sentence:
_________________________ is the process of collecting and distributing performance
information including status reports, progress measurements, and forecasts.
_________________________ is the process of collecting and distributing performance
information including status reports, progress measurements, and forecasts.
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should respond to the risk with the preplanned risk response?
정답: A
설명: (DumpTOP 회원만 볼 수 있음)
You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?
정답: A
설명: (DumpTOP 회원만 볼 수 있음)