최신 AgilePM-Practitioner 무료덤프 - APMG-International Agile Project Management (AgilePM) Practitioner

Which statement should be recorded under the Change Management Team and Relationships heading?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people ' s social experience to guide management actions. Answer the following questions about the use of David Rock ' s SCARF framework to increase the motivation for change.
On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be 'hot-desks,' not used by staff permanently based in the office.
Is this an appropriate approach to reward the brain in the need for 'certainty,' and why?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off BECAUSE The aim of the Investigation step within each Timebox is to complete as much of the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the work of each Timebox.

정답:

Explanation:
For each line, here is the appropriate option from A to E that applies:
* All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
* E. False (Assertion) False (Reason)
* Rationale: It is not practical or in line with Agile principles to consolidate all internal works into one Structured Timebox, as the work will likely need to be spread over multiple Timeboxes.
Additionally, the Investigation step involves agreeing on how to meet the requirements of the Timebox, not necessarily consolidating all work into one.
* Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: While it is true that acceptance criteria should be agreed upon during the Timebox Kick-Off, the reason given is incorrect because the aim of the Investigation step is not necessarily to complete as much development work as possible but to plan and understand the work that will be carried out.
* It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Each Timebox should indeed include both Evolutionary Development and a Deployment phase. This assertion and reason correctly align with the concept of Timeboxing in Agile.
* It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The typical Timebox Plan does provide a schedule of high-level activities for the imminent Project Increment, which would include planning for deployment.
* It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
* C. True (Assertion) False (Reason)
* Rationale: While it is true that Earth Excavations should create a detailed plan for their activities in Timebox C, the reason is incorrect as the Solution Development Team is not solely responsible for planning all work details within a Timebox. This task would typically be a collaborative effort involving all relevant parties.
Which approach is the MOST likely to ensure that the participants apply themselves productively to the co-design tasks in a workshop?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

정답: B,C
설명: (DumpTOP 회원만 볼 수 있음)

정답:

Explanation:
Here the task is to identify which AgilePM principle is most significantly compromised in each case, based on the behavior or concern described.
1. Lee Tan is skeptical about agile ways of working and dismisses Sprint Reviews as a waste of time, creating tension and hindering collective alignment.
answer: G - Communicate continuously and clearly
Sprint Reviews are a core mechanism for transparency, feedback, shared understanding, and alignment. If Lee dismisses them and creates tension around them, the biggest principle being undermined is continuous and clear communication .
Why not just Collaborate ?
That is also affected, but the most direct issue here is rejection of a structured communication and feedback forum. Sprint Reviews exist to keep business and delivery aligned through ongoing communication.
So the most significantly compromised principle is:
1 # G
2. Priya insists that all aspects of the aromatherapy oil, including packaging and marketing, must be fully defined before development, causing concern among teammates.
answer: F - Develop iteratively
This directly conflicts with AgilePM's belief that not everything must be fully detailed upfront. AgilePM supports evolving detail over time through learning, feedback, and iteration.
Priya's position reflects a predictive mindset: define everything first, then build. AgilePM instead encourages starting from sufficient understanding and refining as the team learns more.
So the most significantly compromised principle is:
2 # F
3. Lee Tan is reluctant to release operational staff to act as Business Advisors for the Spa's booking system, prioritizing short term efficiencies. He assumes business requirements are obvious and Developers can proceed without direct business input.
answer: A - Focus on the business need
This is a strong violation of the principle of focusing on the business need . AgilePM depends on active business involvement to ensure that what is delivered genuinely meets operational and strategic needs.
If operational staff are not made available as Business Advisors, the team risks building a solution based on assumptions rather than real business understanding. That undermines the ability to ensure the solution is fit for business purpose.
Why not Collaborate ?
That is involved too, but the core failure is the assumption that delivery can proceed without direct business input. That most fundamentally threatens alignment to the real business need.
So the most significantly compromised principle is:
3 # A
4. Many Delivery Team members in Spa operations, marketing, and IT are part-time and their daily responsibilities are taking priority over project roles. Their limited availability raises concerns about meeting Sprint commitments.
answer: B - Deliver on time
This concern most clearly threatens the AgilePM principle of delivering on time . If part-time participation and competing priorities reduce team capacity, Sprint commitments become unreliable and timeboxes are put at risk.
AgilePM places strong emphasis on protecting time and using prioritization and commitment to ensure timely delivery. If people are not sufficiently available, timely delivery becomes difficult.
Why not Demonstrate control ?
That could also be affected, but the scenario explicitly points to concern about meeting Sprint commitments, which most directly maps to delivery timeliness.
So the most significantly compromised principle is:
4 # B
5. IT developers worry that testing critical booking system integrations can only happen at the end of the Project Increment, rather than being embedded within each iteration.
answer: D - Never compromise quality
This most directly undermines never compromise quality . AgilePM expects quality to be built in throughout delivery, not deferred until the end. Leaving critical integration testing until the end increases the risk of defects, surprises, rework, and unstable delivery outcomes.
Testing should be integrated into the iterative process so that quality is assessed continuously and problems are found early.
Why not Develop iteratively ?
Iterative development is also relevant, but the main concern here is not iteration itself. It is that quality assurance, especially critical integration testing, is being postponed. That most clearly violates the principle of protecting quality.
So the most significantly compromised principle is:
5 # D
Brinda Vyas and Mira Bachar have agreed to use content from a marketing brochure to describe guest-centric Product Goals for the Eco-Spa. These goals describe specific treatments that the Spa might offer and will be used to identify prioritizable Product Backlog items that could contribute to that treatment. One such Product Goal is described as:
Hydrotherapy in Mineral-Rich Spring Pools
Immerse yourself in mineral-rich hydrotherapy pools designed to soothe muscies, improve circulation, and promote deep relaxation. Experience the gentle power of temperature-controlled waters and therapeutic massage jets in a lush and tranquil tropical garden setting and let nature ' s healing embrace rejuvenate both your body and your mind.
In addition to the Developers, the teams include:

(Which of the following actions is appropriate when defining prioritizable Product Backlog items for the ' Hydrotherapy in Mineral-Rich Spring Pools ' Product Goal?)

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
The Applications Manager agreed to the acquisition by UniCo because they knew that growing Selco needed more investment than they could raise and that they personally didn't have the skill set to move from technical leader to business leader.
Which preference does this behavior BEST display?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Which 2 statements represent appropriate entries for the Development
Approach Definition?

정답: C,E
설명: (DumpTOP 회원만 볼 수 있음)
What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which ' event ' BEST offers the opportunity to connect learning to the wider change initiative?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)

우리와 연락하기

문의할 점이 있으시면 메일을 보내오세요. 12시간이내에 답장드리도록 하고 있습니다.

근무시간: ( UTC+9 ) 9:00-24:00
월요일~토요일

서포트: 바로 연락하기